Tarrant County College Southeast Cooling Tower Replacement
Under a five-year master services agreement, Farnsworth Group performed commissioning for an upgrade project that involved the installation of three new cooling towers, three new condenser water pumps, a state-of-the-art disk filtration system, upgraded building automation system controls for the new mechanical equipment, and new panelboards.
During the design review phase, a single review uncovered 11 issues, all of which were promptly identified, addressed, and successfully resolved. These issues primarily revolved around optimizing the controllability of HVAC systems by adjusting the building automation system.
As the project progressed from design to construction and acceptance phases, nine additional issues were identified and effectively communicated to the design and construction teams.